Projects

29 September، 2022

Overhauling for HCL furnace E – CA Plant

Complete overhauling for HCL furnace E (dismantling, inspection, replacement, cleaning, and boxing-up).
28 September، 2022

Mechanical installation, commissioning and startup for PVC2 & VCM3 of TCI SANMAR

A mechanical installation, commissioning and startup contract has been signed for TCI SANMAR CHEMICALS S.A for following plants VCM3 Plant PVC2 Plant from period 2018 / […]
28 September، 2022

salt washer line-1 – C.A Plant

Revamping salt washer line-1(dismantling, inspection, replacement, painting, cleaning, and boxing-up).                      duration of work : 20 day
28 September، 2022

Cell house electrolyzes – C.A Plant

Revamping Cell house electrolyzes (dismantling, inspection, replacement gasket and membrane, cleaning, and boxing-up).
28 September، 2022

PVC-1 Plant

Installation and commissioning for new five transformers 22KV/0.5KV,CB commissioning with all required tests.
28 September، 2022

AEP Plant Shutdown

Date : April 2022 The heat exchanger removed and new one erected on its foundation, This is with the high risk due to no entrance for […]
28 September، 2022

VCM Plant Shutdown

Complete shutdown for high hazard six columns (dismantling, inspection, welding, cleaning, and boxing-up). Dewatering Column, Recovery Column, HCL Column, VCM Column, Quench Column, Vent Scrubber.
19 March، 2022

Change Duct of Clinker Cooler

Scope of Work: change the duct of cooler diameter 3600mm, elbow 90 degree, and transition from circular to Rectangular.
19 March، 2022

Replacement outlet shell sections of Cement Kiln#2 – Suez Cement Plant

The project concerns of the replacement of new two shell sections for Kiln#2 replacing the following two shell section: ➢ The Outlet heavy section under tyre#3 […]
21 September، 2021

Transfer Alternative Fuel system from Line 5 to Line 1 – LAFARGE CEMENT

Dismantling, transferring and installing the alternative fuel system from line 5 to line 1 The project implementation period is 90 days Scope of Works: Dismantling all […]
9 September، 2021

Shutdown Kattameya Cement Plant 8/2021

Menco Group has successfully completed a maintenance overhaul shutdown 8-2021 for following area: Kiln and kiln feed shutdown  Raw mills 1,2 Clinker crusher & Heat Exchanger […]
25 February، 2021

Change the duct of By-pass GCT – LAFARGE CEMENT PLANT

Fabrication & Change the new Duct with Axial Hinge Expansion Joint    
24 January، 2021

Rehabilitation ESP Filter – SINAI CEMENT

Date : 4/1/2021 to 22/1/2021 Scope of Project: Dismantle the High voltage transformer & lowering to ground Remove the outer Upper Cover of ESP Filter Remove […]
16 January، 2021

Overhaul of cement mill 8 and all related equipment – Helwan Cement Plant

Extra main equipment mandatory by supplier: RIMMER, DRILLER, HYDRAULIC JACK 500 1-Removal of Trunnion 2-Removal of Journal Bearing and Housing 3-Repair Flange of Mill Head by […]
16 January، 2021

Fabrication Ring for Cement mill 8 – HELWAN CEMENT

Fabrication Ring Plate O.D 3300 / I.D 3100 – Thickness 60mm with 48 holes Diameter 34mm
14 November، 2020

Completely replacement Clinker laminated box Conveyor – Helwan Cement Plant

Scope of Work: Date : 18/10/2020 Disconnect the old laminated box conveyor and remove it. Replace the old rails and supports by new one, and we […]
2 November، 2020

Shutdown of Pre-heater line 4 Oct.2020 – LAFARGE EGYPT CEMENT

Scope of Works: Date : Oct. 2020 Pre-heater Tower Change the worn sheet metal Change the big Damper for tertiary air duct Change all material piping
13 August، 2020

C.M 7 and all related equipment SD – Helwan Cement Plant

Scope of Works: Cement Mill Replace complete 4 rows lining plates of the inlet head types B, C, D & E Repair complete wearing plates of […]
8 August، 2020

Coal Mill 2 Separator – SINAI CEMENT PLANT

Scope of Works: Change separator rotor Adjust the top seal clearance Change all louvers Change all wear plates Repair worn out steel parts at reject cone […]
21 July، 2020

Insulation Works for E.P Filter – SINAI CEMENT PLANT

Scope of Works: 1000 sq.m. thermal insulation works have been completed with the rock wool of the E.P filter – Remove the old insulation. – Make […]