0020227544109
infoegypt@mencogroup.com
Home
Contact us
Site Map
Meet Menco
Our Sister Company
Metaje Company
Projects
Turnkey Projects
Cement Plants
Petrochemical Plants
Fabrications
Fire Fighting
Services
Mechanical Services
Maintenance Services
Fabrication
Installation
Dismantling works
Electrical services
Sustainability
HSE
Shutdown of Pre-heater line 4 Oct.2020 – LAFARGE EGYPT CEMENT
Scope of Works:
Date : Oct. 2020
Pre-heater Tower
Change the worn sheet metal
Change the big Damper for tertiary air duct
Change all material piping
You may be also interested in
20 April، 2024
Kiln 1 section replacement with length = 36.7 meters (Divided in 5 sections) at Helwan Cement Plant
Read more
3 February، 2024
Supply, fabricate, transport and install of Bypass Condition Tower and its ducts line 3 at Lafarge Cement Plant
Read more
29 September، 2022
Overhauling for HCL furnace E – CA Plant
Read more
0020227544109
infoegypt@mencogroup.com
Home
Contact us
Site Map