Shutdown of Pre-heater line 4 Oct.2020 – LAFARGE EGYPT CEMENT
Scope of Works:
Date : Oct. 2020
Pre-heater Tower
Change the worn sheet metal
Change the big Damper for tertiary air duct
Change all material piping
You may be also interested in
3 February، 2024
Supply, fabricate, transport and install of Bypass Condition Tower and its ducts line 3 at Lafarge Cement Plant
Read more
29 September، 2022
Overhauling for HCL furnace E – CA Plant
Read more
28 September، 2022
Mechanical installation, commissioning and startup for PVC2 & VCM3 of TCI SANMAR
Read more
0020227544109
infoegypt@mencogroup.com
Home
Contact us
Site Map